Monday 27th January 2014
Today we received our Social action assignment, our task is to produce an anti-smoking video along with full pre-production paper work and an active production blog. I also produced some research that will assist In the production of my idea which is in development.

Thursday 30th January 2014

Today we pitched our anti-smoking video ideas, two of these ideas will go on to be made into a short film. Once everyone had pitched their idea Neil and Kelly decided that three films would be made instead of two. The three ideas to be chose were Ryans, Isaaks and Jordans. I paired up with Jordan as we had similar ideas so we could provide a more thought out way of looking at how to film it.
Monday 3rd February 2014

Today we had a short production meeting, we made the decision to have attempted some form of filming by Friday the 7th of February and that if not filming would commence Monday the 10th of February. We also chose our cast, this was based upon whether people smoked, their appearance and whther they fit the character profile. We decided on 2 actors, Sam Hitchcliff and Jacob Hanson.

Tuesday 4th February 2014

Today we produced a shot list for my short film which is set to be filmed on the 7th of February. As well as the shot list i also produced a make-up ideas page for my make-up artist(s)

Wednesday 5th February 2014

Today we performed a location recce and risk assessment as well as gaining permission to film at our chosen location, the Dubliners pub, after this we had a short informal meeting with the actors, discuccing our plans for filming.

Thursday 6th February 2014

Today was our planned filming day, we went to the dubliners and began filming, we had planned to film from half nine to twelve which turned out to be too long as all the necessary footage had been filmed by twenty past 11. After filming I captured the footage and began putting the footage together, after assesment of the footage I decided a reshoot was in order for 3 of the shots as there was some poor framing and acting that I feel could be improved.

Tuesday 11th February 2014

Today was our planned reshoot day, we arrived at our location, the dubliners, at half nine and began filming at twenty to ten, we filmed all the shots we needed and were done just after ten o clock. We returned to college and captured the footage.

Thursday 13th february 2014

Today the edit was finished. We replaced poor shots with the re-shoot shots and tidying up clips that were on screen for too long and replacing poor audio.